Workflow inside workflow

Hello everybody,
not sure how to formulate this tricky question.
I have a workflow, that contains step enroll into another workflow in the middle of the flow.
The thing is that I need the “inserted” workflow to be completed before the contact moves on in the original workflow.
Does the original workflow wait? Or shall I use some delay function to make sure it will not continue before the “inserted” (very short 3 steps) workflow is completed.
Please advice,
Thanks
Adam

Hi @Adam_D

Even if you know how long the 2nd workflow should take to complete and you could insert a delay for a longer period of time - 1 hour vs 1 day for example, there is still some risk here. By far the safest approach is to split this into three workflows and have the second enrol the contact in the third once other actions are completed.

Hope this helps?