Automatically move pipeline stages based on close date
SOLVE
Hello,
I'm trying to move deals in a Renewals pipeline automatically based on their close date. [The screenshot attached should help to easily understand the business need]
I have troubles understading how re-enrollment works. In an ideal world, all deals in this pipeline will be enrolled daily, and follow a If/Then branch Close date is less than 60 days, move to the next stage etc. I don't find a way to have this automatic daily re-enrollment. Any idea?
Looking back at my outline, I noticed a couple of things to update.
1. Need to add the current stage, as once a deal is moved to the next stage, it doesn't need to re-enroll.
2. the 4th workflow should be "close date is more than than 1 day ago" and not "close date is more than than 1 day now"
Not sure of the specifics of your use case and if close dates potentially get updated. However, you don't necessarily need the activity and re-enrollment. This would still move a deal through the stages as it hit the date thresholds.
Automatically move pipeline stages based on close date
SOLVE
You really need an inclusion vs exclusion based trigger for re-enrollment. Last activity is more than X days ago.
Based on your pipline stage viewI would create multiple workflows and use the date in the trigger criteria. Use last activity as re-enrollment trigger. This re-enroll if no activity has taken place in X days.
Looking back at my outline, I noticed a couple of things to update.
1. Need to add the current stage, as once a deal is moved to the next stage, it doesn't need to re-enroll.
2. the 4th workflow should be "close date is more than than 1 day ago" and not "close date is more than than 1 day now"
Not sure of the specifics of your use case and if close dates potentially get updated. However, you don't necessarily need the activity and re-enrollment. This would still move a deal through the stages as it hit the date thresholds.