I could use some shared brain power on this one - I am trying to create some non-linear forecasting based on project resource style line items and I cannot for the life of me figure out the best route to go without it being overly complicated with a million calculation fields in the background
The Line Items are the "resources" needed for the client project so I may have, for example, 5 Managers allocated for 5 days each in month 1, but in month 2 I might have 3 and month 3 it might be just 1
I'm looking to try and be able to see that month 1 has 50% of the total value, month 2 has 30% and month 3 has 20%
One issue comes when the days they are allocated splits across 2 months - so i may have a Manager line item with start date of 30th October and end date of 3rd November. I would need the allocation of the value to be split with 2 days in October and 3 in November
Second issue comes when a Manager that is allocated in one block has to then have another block added further down the project line
My brain is spinning and any thoughts would be greatly appreciated
I would be lying if say my head is not spinning 😵💫 - its a complex use-case:
Honestly, instead of doing this on line items, I would prefer a custom object here looking at various layers of data points and surely you would need couple of date stamp properties and calculation properties.
As a next step, I recommend you build a solution schema/diagram for this and try to visualize this problem + potential solutions on Miro or Lucid and then share it here.
I would be lying if say my head is not spinning 😵💫 - its a complex use-case:
Honestly, instead of doing this on line items, I would prefer a custom object here looking at various layers of data points and surely you would need couple of date stamp properties and calculation properties.
As a next step, I recommend you build a solution schema/diagram for this and try to visualize this problem + potential solutions on Miro or Lucid and then share it here.