Hey all,

I have a question regarding the ‘Delay until event’ type. If set like that (image below) does that mean that if anytime during this 1 day an enrolled user submits a form, it will immediately go to the correspoding branch or it will wait the 1 day to finish? Or only the user that don’t meet the criteria will wait the delay time and then exist and go to the other branch ‘Event not met’?

Thanks!

Hi @KSergieva11,

If contacts submit the form, they will immediately move on (left branch). If they do not submit the form, the workflow will wait for up to a day, then send them to the right branch.